88
Units Launched
84
Units Sold (Cumulative)
4
Unsold Balance
Construction (Q1 2026)
₹0.00 Cr
Funds Collected
95%
Inventory Sold
Data source: Haryana RERA quarterly progress reports (QPRs) Figures are compiled from public filings on haryanarera.gov.in and were last synced on 03 Jul 2026. Numbers reflect what developers report to the regulator and may lag on-ground status. Verify current details on the official portal before making decisions.

RERA Registration Validity

The developer has committed to complete this project within its RERA registration window.

Registered up to 31 Mar 2028633 days remaining

Quarter-by-Quarter Filings

1 quarterly reports captured (Q1 2026 – Q1 2026)

QuarterUnits LaunchedBooked (Qtr)Construction %Funds Collected
Q1 2026 88 84 ₹0.00 Cr

Considering JMS GROUP THE MAJESTIC ABODE?

Talk to our local team — we'll give you the unfiltered picture, including things the brochure won't tell you.

Ask on WhatsApp

More from this developer: see JMS REALTY DEVELOPERS LLP's full RERA track record →

Facebook Instagram YouTube WhatsApp LinkedIn
Ahana Online