THE GROVE

RERA project health report — how this project is actually selling and progressing, from the developer's own quarterly filings with the Haryana RERA regulator.

DLF LIMITED DLF 5, SECTOR 54 GGM/538/270/2022/13 DATED 21.02.2022
292
Units Launched
373
Units Sold (Cumulative)
0
Unsold Balance
Construction (Q1 2025)
₹0.02 Cr
Funds Collected
128%
Inventory Sold
Data source: Haryana RERA quarterly progress reports (QPRs) Figures are compiled from public filings on haryanarera.gov.in and were last synced on 03 Jul 2026. Numbers reflect what developers report to the regulator and may lag on-ground status. Verify current details on the official portal before making decisions.

RERA Registration Validity

The developer has committed to complete this project within its RERA registration window.

Registered up to 31 Dec 2025expired 188 days ago (check the official portal for extensions)

Sales Velocity — Units Booked Per Quarter

Green bars = units the developer reported as booked in that quarter. Blue line = total inventory launched to date.

Construction Progress

Percentage of construction completed, as reported to the regulator each quarter.

Quarter-by-Quarter Filings

12 quarterly reports captured (Q2 2022 – Q1 2025)

QuarterUnits LaunchedBooked (Qtr)Construction %Funds Collected
Q1 2025 292 2 ₹0.00 Cr
Q4 2024 292 3 ₹0.00 Cr
Q3 2024 292 8 ₹0.00 Cr
Q2 2024 292 0 ₹0.00 Cr
Q1 2024 292 12 ₹0.00 Cr
Q4 2023 292 2 ₹0.00 Cr
Q3 2023 292 10 ₹0.00 Cr
Q2 2023 292 21 ₹0.00 Cr
Q1 2023 292 23 ₹0.00 Cr
Q4 2022 292 240 ₹0.00 Cr
Q3 2022 292 52 ₹0.00 Cr
Q2 2022 292

Considering THE GROVE?

Talk to our local team — we'll give you the unfiltered picture, including things the brochure won't tell you.

Ask on WhatsApp

More from this developer: see DLF LIMITED's full RERA track record →

Facebook Instagram YouTube WhatsApp LinkedIn