THE BILLIONAIRE RESIDENCES

RERA project health report — how this project is actually selling and progressing, from the developer's own quarterly filings with the Haryana RERA regulator.

KVELL INFRASTRUCTURE LLP SECTOR-2,GWAL PAHARI, DISTRICT GURUGRAM,HARYANA GGM/793/525/2024/20 DATED 11.03.2024
89
Units Launched
50
Units Sold (Cumulative)
39
Unsold Balance
Construction (Q1 2026)
₹0.00 Cr
Funds Collected
56%
Inventory Sold
Data source: Haryana RERA quarterly progress reports (QPRs) Figures are compiled from public filings on haryanarera.gov.in and were last synced on 03 Jul 2026. Numbers reflect what developers report to the regulator and may lag on-ground status. Verify current details on the official portal before making decisions.

RERA Registration Validity

The developer has committed to complete this project within its RERA registration window.

Registered up to 30 Jun 2028724 days remaining

Sales Velocity — Units Booked Per Quarter

Green bars = units the developer reported as booked in that quarter. Blue line = total inventory launched to date.

Construction Progress

Percentage of construction completed, as reported to the regulator each quarter.

Quarter-by-Quarter Filings

8 quarterly reports captured (Q2 2024 – Q1 2026)

QuarterUnits LaunchedBooked (Qtr)Construction %Funds Collected
Q1 2026 89 2 ₹0.00 Cr
Q4 2025 178 0 ₹0.00 Cr
Q3 2025 89 8 ₹0.00 Cr
Q2 2025 89 6 ₹0.00 Cr
Q1 2025 89 7 ₹0.00 Cr
Q4 2024 89 24 ₹0.00 Cr
Q3 2024 89 3 ₹0.00 Cr
Q2 2024 89 0

Considering THE BILLIONAIRE RESIDENCES?

Talk to our local team — we'll give you the unfiltered picture, including things the brochure won't tell you.

Ask on WhatsApp

More from this developer: see KVELL INFRASTRUCTURE LLP's full RERA track record →

Facebook Instagram YouTube WhatsApp LinkedIn
Ahana Online