TATVA ESTATES

RERA project health report — how this project is actually selling and progressing, from the developer's own quarterly filings with the Haryana RERA regulator.

ALTON BUILDTECH INDIA PVT LTD SECTOR 99A, GURGAON GGM/699/431/2023/43 DATED 02.03.2023
69
Units Launched
14
Units Sold (Cumulative)
55
Unsold Balance
Construction (Q1 2026)
₹0.00 Cr
Funds Collected
20%
Inventory Sold
Data source: Haryana RERA quarterly progress reports (QPRs) Figures are compiled from public filings on haryanarera.gov.in and were last synced on 03 Jul 2026. Numbers reflect what developers report to the regulator and may lag on-ground status. Verify current details on the official portal before making decisions.

RERA Registration Validity

The developer has committed to complete this project within its RERA registration window.

Registered up to 04 Dec 2027515 days remaining

Sales Velocity — Units Booked Per Quarter

Green bars = units the developer reported as booked in that quarter. Blue line = total inventory launched to date.

Construction Progress

Percentage of construction completed, as reported to the regulator each quarter.

Quarter-by-Quarter Filings

12 quarterly reports captured (Q2 2023 – Q1 2026)

QuarterUnits LaunchedBooked (Qtr)Construction %Funds Collected
Q1 2026 69 0
Q4 2025 69 ₹0.00 Cr
Q3 2025 69 0 ₹0.00 Cr
Q2 2025 69 0 ₹0.00 Cr
Q1 2025 69 0 ₹0.00 Cr
Q4 2024 ₹0.00 Cr
Q3 2024 69 ₹0.00 Cr
Q2 2024 69 0 ₹0.00 Cr
Q1 2024 69 0 ₹0.00 Cr
Q4 2023 69 0 ₹0.00 Cr
Q3 2023 69 7 ₹0.00 Cr
Q2 2023 69 7 ₹0.00 Cr

Considering TATVA ESTATES?

Talk to our local team — we'll give you the unfiltered picture, including things the brochure won't tell you.

Ask on WhatsApp

More from this developer: see ALTON BUILDTECH INDIA PVT LTD's full RERA track record →

Facebook Instagram YouTube WhatsApp LinkedIn
Ahana Online