M3M SOULITUDE 2
RERA project health report — how this project is actually selling and progressing, from the developer's own quarterly filings with the Haryana RERA regulator.
RERA Registration Validity
The developer has committed to complete this project within its RERA registration window.
Registered up to 03 Apr 2027 — 270 days remaining
Sales Velocity — Units Booked Per Quarter
Green bars = units the developer reported as booked in that quarter. Blue line = total inventory launched to date.
Construction Progress
Percentage of construction completed, as reported to the regulator each quarter.
Quarter-by-Quarter Filings
6 quarterly reports captured (Q4 2024 – Q1 2026)
| Quarter | Units Launched | Booked (Qtr) | Construction % | Funds Collected |
|---|---|---|---|---|
| Q1 2026 | 887 | 0 | — | ₹0.00 Cr |
| Q4 2025 | 887 | 4 | — | ₹0.00 Cr |
| Q3 2025 | 887 | 10 | — | ₹0.00 Cr |
| Q2 2025 | 887 | 10 | — | ₹0.00 Cr |
| Q1 2025 | 887 | 250 | — | ₹0.00 Cr |
| Q4 2024 | 887 | 327 | — | ₹0.00 Cr |
Considering M3M SOULITUDE 2?
Talk to our local team — we'll give you the unfiltered picture, including things the brochure won't tell you.
More from this developer: see AAWAM RESIDENCY PRIVATE LIMITED's full RERA track record →