858
Units Launched
768
Units Sold (Cumulative)
90
Unsold Balance
Construction (Q1 2026)
₹0.00 Cr
Funds Collected
90%
Inventory Sold
Data source: Haryana RERA quarterly progress reports (QPRs) Figures are compiled from public filings on haryanarera.gov.in and were last synced on 03 Jul 2026. Numbers reflect what developers report to the regulator and may lag on-ground status. Verify current details on the official portal before making decisions.

RERA Registration Validity

The developer has committed to complete this project within its RERA registration window.

Registered up to 31 Aug 202655 days remaining

Sales Velocity — Units Booked Per Quarter

Green bars = units the developer reported as booked in that quarter. Blue line = total inventory launched to date.

Construction Progress

Percentage of construction completed, as reported to the regulator each quarter.

Quarter-by-Quarter Filings

13 quarterly reports captured (Q1 2023 – Q1 2026)

QuarterUnits LaunchedBooked (Qtr)Construction %Funds Collected
Q1 2026 858 8 ₹0.00 Cr
Q4 2025 858 23 ₹0.00 Cr
Q3 2025 858 19 ₹0.00 Cr
Q2 2025 858 23 ₹0.00 Cr
Q1 2025 858 15 ₹0.00 Cr
Q4 2024 858 30 ₹0.00 Cr
Q3 2024 858 79 ₹0.00 Cr
Q2 2024 858 98 ₹0.00 Cr
Q1 2024 858 73 ₹0.00 Cr
Q4 2023 858 64 ₹0.00 Cr
Q3 2023 858 48 ₹0.00 Cr
Q2 2023 858 123 ₹0.00 Cr
Q1 2023 858 165 ₹0.00 Cr

Considering M3M PARAGON57?

Talk to our local team — we'll give you the unfiltered picture, including things the brochure won't tell you.

Ask on WhatsApp

More from this developer: see PARYAPT INFRASTRUCTUREPRIVATE LIMITED's full RERA track record →

Facebook Instagram YouTube WhatsApp LinkedIn
Ahana Online