M3M ANTALYA HILLS PHASE II

RERA project health report — how this project is actually selling and progressing, from the developer's own quarterly filings with the Haryana RERA regulator.

LOON LAND DEVELOPMENT LIMITED SECTOR 79, GURUGRAM GGM/662/394/2023/06 DATED 12.01.2023 (SUPERSEDED BY GGM/833/565/2024/60 DATED 03.06.2024) Lapsed Project
1,392
Units Launched
1,931
Units Sold (Cumulative)
0
Unsold Balance
Construction (Q3 2024)
₹0.01 Cr
Funds Collected
139%
Inventory Sold
Data source: Haryana RERA quarterly progress reports (QPRs) Figures are compiled from public filings on haryanarera.gov.in and were last synced on 03 Jul 2026. Numbers reflect what developers report to the regulator and may lag on-ground status. Verify current details on the official portal before making decisions.

RERA Registration Validity

The developer has committed to complete this project within its RERA registration window.

Registered up to 30 Jun 2026expired 7 days ago (check the official portal for extensions)

Sales Velocity — Units Booked Per Quarter

Green bars = units the developer reported as booked in that quarter. Blue line = total inventory launched to date.

Construction Progress

Percentage of construction completed, as reported to the regulator each quarter.

Quarter-by-Quarter Filings

6 quarterly reports captured (Q2 2023 – Q3 2024)

QuarterUnits LaunchedBooked (Qtr)Construction %Funds Collected
Q3 2024 1,392 20 ₹0.00 Cr
Q2 2024 1,392 23 ₹0.00 Cr
Q1 2024 2,068 463 ₹0.00 Cr
Q4 2023 2,068 370 ₹0.00 Cr
Q3 2023 2,068 145 ₹0.00 Cr
Q2 2023 2,068 910 ₹0.00 Cr

Considering M3M ANTALYA HILLS PHASE II?

Talk to our local team — we'll give you the unfiltered picture, including things the brochure won't tell you.

Ask on WhatsApp

More from this developer: see LOON LAND DEVELOPMENT LIMITED's full RERA track record →

Facebook Instagram YouTube WhatsApp LinkedIn
Ahana Online