DLF REAL ESTATE BUILDERS LIMITED DLF CITY PHASE - I GGM/448/180/2021/16 DATED 25.03.2021
28
Units Launched
26
Units Sold (Cumulative)
2
Unsold Balance
Construction (Q2 2024)
₹0.00 Cr
Funds Collected
93%
Inventory Sold
Data source: Haryana RERA quarterly progress reports (QPRs) Figures are compiled from public filings on haryanarera.gov.in and were last synced on 03 Jul 2026. Numbers reflect what developers report to the regulator and may lag on-ground status. Verify current details on the official portal before making decisions.

RERA Registration Validity

The developer has committed to complete this project within its RERA registration window.

Registered up to 28 Feb 2024expired 860 days ago (check the official portal for extensions)

Sales Velocity — Units Booked Per Quarter

Green bars = units the developer reported as booked in that quarter. Blue line = total inventory launched to date.

Construction Progress

Percentage of construction completed, as reported to the regulator each quarter.

Quarter-by-Quarter Filings

13 quarterly reports captured (Q2 2021 – Q2 2024)

QuarterUnits LaunchedBooked (Qtr)Construction %Funds Collected
Q2 2024 28 0 ₹0.00 Cr
Q1 2024 28 0 ₹0.00 Cr
Q4 2023 28 0 ₹0.00 Cr
Q3 2023 28 0 ₹0.00 Cr
Q2 2023 ₹0.00 Cr
Q1 2023 28 -1 ₹0.00 Cr
Q4 2022 28 0 ₹0.00 Cr
Q3 2022 28 -1 ₹0.00 Cr
Q2 2022 28 1 ₹0.00 Cr
Q1 2022 28 0 ₹0.00 Cr
Q4 2021 28 0 ₹0.00 Cr
Q3 2021 28 0 ₹0.00 Cr
Q2 2021 28 27 ₹0.00 Cr

Considering INDEPENDENT FLOORS AT DLF CITY PHASE I?

Talk to our local team — we'll give you the unfiltered picture, including things the brochure won't tell you.

Ask on WhatsApp

More from this developer: see DLF REAL ESTATE BUILDERS LIMITED's full RERA track record →

Facebook Instagram YouTube WhatsApp LinkedIn
Ahana Online