Gurgaon
HEMIS ONE
Builder: HEMIS INFRASTRUCTURE AND DEVELOPERS
RERA No: GGM/1052/784/2026/24 DATED 20.03.2026
Registered Upto: 23 Dec 2029
QPRs Captured: 1
Reporting Period: Q2 2026 → Q2 2026
Last Synced: 29 Aug 2026 22:24
Total Units
86
as of Q2 2026
Units Sold (Cumulative)
2
2.3% of inventory · +2 in Q2 2026
Units Unsold (Balance)
84
remaining inventory
Capital Collected
₹0.4Cr
from allottees · across 1 quarters
Expenditure (drawn from escrow)
₹0.2Cr
total amount withdrawn
Latest Construction %
—
not reported
Sold vs Unsold Trend
Green + Red = Total Inventory at end of each quarterCapital Collected vs Expenditure
Per-quarter bars (₹ Lakh) · cumulative line · red = amount drawn from escrowAll Quarterly Reports
1 quarters| Quarter | Period | Total Units | Sold | Balance | Sold % | Funds Collected (₹L) | Const % |
|---|---|---|---|---|---|---|---|
| Q2 2026 | — → — | 86 | 2 | 84 | 2.3% | 36 | — |