Gurgaon
DELPHINE CENTRAL PARK ESTATES PHASE I
Builder: ST. NICHOLAS ESTATE DEVELOPMENT PVT LTD
RERA No: GGM/996/728/2025/99 DATED 16.10.2025
Registered Upto: 31 Aug 2032
QPRs Captured: 1
Reporting Period: Q1 2026 → Q1 2026
Last Synced: 13 Jul 2026 17:05
Total Units
601
as of Q1 2026
Units Sold (Cumulative)
99
16.5% of inventory · +99 in Q1 2026
Units Unsold (Balance)
502
remaining inventory
Capital Collected
₹40.1Cr
from allottees · across 1 quarters
Expenditure (drawn from escrow)
—
not reported
Latest Construction %
—
not reported
Sold vs Unsold Trend
Green + Red = Total Inventory at end of each quarterCapital Collected
Per-quarter bars (₹ Lakh) · cumulative lineAll Quarterly Reports
1 quarters| Quarter | Period | Total Units | Sold | Balance | Sold % | Funds Collected (₹L) | Const % |
|---|---|---|---|---|---|---|---|
| Q1 2026 | — → — | 601 | 99 | 502 | 16.5% | 4,009 | — |